WIESBADEN, Germany—The physical fitness facility on Clay Kaserne is sporting a new basketball court, thanks to repairs just finished July 14.
U.S. Army Garrison Wiesbaden Commander, Col. Mario Washington, Mitchell Jones, deputy to the garrison commander, Sascha Richardson and Klaus Hahn cut the ribbon to officially open the court July 22.
Preliminary planning began in September 2019 with construction starting in November 2020 to replace the original court floor from 2006.
The approximate cost for the new flooring is $1.5 million and included minor repairs to accommodate wood expansion due to humidity along with it becoming FIBA Euroleague certified with a completely new substructure. The court is now a mutli-purpose sports flooring with the Wiesbaden Garrison Crest as the center court logo!
Date Taken: | 07.22.2021 |
Date Posted: | 07.28.2021 07:23 |
Photo ID: | 6752894 |
VIRIN: | 210722-O-MV779-102 |
Resolution: | 1088x1299 |
Size: | 369.2 KB |
Location: | WIESBADEN, HESSEN, DE |
Web Views: | 250 |
Downloads: | 6 |
This work, Clay Kaserne's physical fitness facility gets new basketball court, by Ila Dermanoski, identified by DVIDS, must comply with the restrictions shown on https://www.dvidshub.net/about/copyright.