Work continues for the second phase (Phase B) of the Naval Submarine Base (NSB) Kings Bay Dry Dock Recapitalization Project, which is scheduled to be completed by Oct. 2022. Naval Facilities Engineering Systems Command (NAVFAC) Southeast awarded a $41.2 million modification Oct. 14 to exercise the third through ninth options for the third phase (Phase C) of the project. This modification allows the Resident Officer in Charge of Construction (ROICC) Trident team to plan and prepare for the final work required to bring the Trident Refit Facility (TRF) at NSB Kings Bay back to full mission capability.