U.S. Army Corps of Engineers Pittsburgh District contractors use a bulldozer to smoothen the subgrade for a concrete batch plant staging area at Montgomery Locks and Dam in Monaca, Pennsylvania, Sept. 17, 2024.
The batch plant site is nearly complete as contractors resurface and level the pad, add fencing, and other improvements. The site will allow a future contractor to operate a batch plant to produce 400,000 cubic yards of concrete for a new navigation chamber at Montgomery Locks and Dam.
The project will replace the auxiliary chamber, measuring 56 feet wide by 360 feet long, with locks measuring 110 feet wide by 600 feet long. The Bipartisan Infrastructure Law provided $857.7 million for construction at the Montgomery facility. The district expects the project to support more than 15,000 jobs nationally throughout the construction period.
Transporting commodities on the waterways is four times less expensive than by truck and 33 percent cheaper than by rail. Between 15 million and 20 million tons of cargo travel on the upper Ohio River each year, including mainly coal, but also coke, petroleum products, raw and finished steel, and aggregates.
(U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Date Taken: | 09.17.2024 |
Date Posted: | 09.23.2024 14:05 |
Photo ID: | 8656920 |
VIRIN: | 240917-A-TI382-1301 |
Resolution: | 6000x4000 |
Size: | 9.28 MB |
Location: | PITTSBURGH, PENNSYLVANIA, US |
Web Views: | 9 |
Downloads: | 2 |
This work, Chipping away old concrete to preserve Montgomery Dam piers for the future [Image 36 of 36], by Michel Sauret, identified by DVIDS, must comply with the restrictions shown on https://www.dvidshub.net/about/copyright.