    F-16s return to new runway at Buckley Air Force Base

    140th Wing, Colorado Air National Guard F-16s return to Buckley Air Force Base

    Photo By Maj. Kinder Blacke | F-16s from the 140th Wing, Colorado Air National Guard begin to return to Buckley Air...... read more read more

    DENVER, COLORADO, UNITED STATES

    07.15.2014

    Story by Capt. Kinder Blacke 

    Colorado National Guard

    BUCKLEY AIR FORCE BASE, Colo. – The Colorado Air National Guard’s F-16 fleet is heading back ahead of schedule to the newly reconstructed runway at Buckley Air Force Base after spending three months at Denver International Airport.

    Personnel from the 140th Wing relocated their flying mission to DIA back in April, with the intent to stay 90 days while the runway at Buckley Air Force Base underwent heavy construction. Fortunately, the operation went as planned and the jets were able to start flying back over the weekend.

    “The transition to and from DIA was seamless,” said Col. Floyd Dunstan, commander, 140th Wing. “Thanks to the huge amount of planning and effort that went into this move, and the tremendous support we received from all of the agencies at DIA, we were able to maintain our 24/7 alert mission and sustain routine training flights throughout the relocation. Now we are excited to return to a much-improved runway.”

    The 140th Civil Engineer Squadron spear-headed the runway construction project, which involved pouring approximately sixty thousand cubic yards of concrete, according to Lt. Col. Tom Niichel, construction manager, 140 CES.

    “We lowered the northern end of the runway a little over seven feet and we put new concrete on both the north and south landing zones,” said Niichel.

    In addition to leveling the runway, the team also replaced the concrete on a large portion of the taxiways and apron due to the effects of alkali-silica reaction, a chemical reaction that had cracked and degraded the surface of the concrete over time, Niichel explained.

    While the entire construction project will not be complete until September, the airfield is fully operational and the first jets touched down at Buckley on Friday, July 11.

    Niichel is hopeful that after this runway overhaul, the airfield will be operational with only routine maintenance for the next 50 years.