    Photo Essay: February 2023 construction operations of $11.96 million transient training brigade headquarters at Fort McCoy, Part VIII

    February 2023 construction operations of $11.96 million transient training brigade headquarters at Fort McCoy

    Photo By Scott Sturkol | The construction area for a future transient training brigade headquarters in the 1600...... read more read more

    The construction area for a future transient training brigade headquarters in the 1600 block on the cantonment area is shown Feb. 15, 2023, at Fort McCoy, Wis.

    A contract, totaling $11,964,432.87, was awarded June 9, 2022, to L.S. Black Constructors to build the fiscal year 2022 Transient Training Brigade Headquarters project at Fort McCoy.

    Construction operations began in August 2022.

    Location of construction is just across the street from where the same contractor has been building two new transient training troop barracks buildings in the same block.

    According to the Fort McCoy Directorate of Public Works Master Planning Division, the brigade headquarters project is based on the denser, more consolidated footprints of Fort McCoy’s Troop Housing Area Development Plan which states “fewer, multiple story buildings allow facilities/functions to be sited closer together, allowing for a more walkable training environment, as well as saving money on utilities.”

    The smaller footprint of the brigade headquarters building plan builds less impervious surface, which generates less stormwater runoff that requires less stormwater management features and allows for additional cost savings.

    The floor plan also is based on the “Operational Readiness Training Complex” standard design and additional square footage has been included in this project to accommodate stair and elevator access to the second floor.”

    Large construction projects like this barracks project also contributes to the economic impact of local communities. Fort McCoy Garrison officials said Fort McCoy’s total economic impact for FY 2021 was an estimated $1.93 billion, above the $1.479 billion reported for FY 2020, garrison officials announced.

    The Fort McCoy Executive Summary, available on the installation website, www.home.army.mil/mccoy, also shows the installation makes continuous improvements to provide a plethora of training capabilities for service members.

    “Throughout the last decade, Fort McCoy experienced unprecedented facility modernization, training area development and expansion, increased training and customer support capability, and improved quality-of-life opportunities,” the summary states.

    The U.S. Army Corps of Engineers is managing the project.

    Learn more about Fort McCoy online at https://home.army.mil/mccoy, on the Defense Visual Information Distribution System at https://www.dvidshub.net/fmpao, on Facebook by searching “ftmccoy,” and on Twitter by searching “usagmccoy.”