A project to complete roofing work that is led by the U.S. Army Corps of Engineers is underway for a hangar at Sparta-Fort McCoy Airport on South Post and for building 2187 on the cantonment area at Fort McCoy.
Jacque McNamee, project engineer for the Louisville District office of the Army Corps of Engineers at Scott Air Force Base, Ill., said a contract is in place that covers “the reroofing work for building (hangar) 6058 and building 2187.”
The contractor on this project is AR6/CRAM Roofing Joint Venture.
McNamee said the scope of work for the hangar covers a complete replacement of the existing flat-roof systems with a new two-ply modified bitumen roof system.
But overall, a lot of work is getting completed to both buildings.
“Miscellaneous repairs are being formed on the metal roof sections, including resealing open head lap joints, valley joints, and ridge cap joints,” McNamee said. “Gutter and downspout joints are also being resealed for proper function.”
The buildings are also getting a new lightning protection system replacement and new fixed ladders between roof sections.
Having construction projects like this completed with local contractors also supports local economies. Fort McCoy’s total economic impact for fiscal year (FY) 2022 was an estimated $2.52 billion, above the $1.93 billion reported for FY 2021, garrison officials announced in March 2023. The data was compiled by Fort McCoy’s Plans, Analysis and Integration Office.
Workforce payroll, operating costs, and other expenditures totaled $629.08 million for FY 2022 compared to $481.6 million for FY 2021.
FY 2022 operating costs of $391.46 million included utilities, physical plant maintenance, repair and improvements, new construction projects, purchases of supplies and services, as well as salaries for civilian contract personnel working at Fort McCoy. Other expenditures accounted for $52.25 million and covered $339,994 in payments to local governments (including land permit agreements, school district impact aid, etc.) as well as $51.91 million in discretionary spending in local communities by service members training and residing at Fort McCoy.
Other factors of economic impact for the fiscal year included more than $42.5 million in military construction on post.
The Fort McCoy Executive Summary, available at https://www.dvidshub.net/unit/FMPAO, also shows the installation makes continuous improvements to the post so the installation is at its best for troops to complete training. So, even a roofing project at the Sparta-Fort McCoy Airport contributes to that effort.
“Throughout the last decade, Fort McCoy experienced unprecedented facility modernization, training area development and expansion, increased training and customer support capability, and improved quality-of-life opportunities,” the summary states. “From unmanned aerial vehicles to urban training facilities, to live-fire ranges and virtual-training environments, Fort McCoy is prepared to meet the training needs of the Army in the 21st century.”
The contractor anticipates being done with the construction phase of this contract by mid-November, McNamee said.
Learn more about Fort McCoy online at https://home.army.mil/mccoy, on the Defense Visual Information Distribution System at https://www.dvidshub.net/fmpao, on Facebook by searching “ftmccoy,” and on Twitter by searching “usagmccoy.”
Also try downloading the Digital Garrison app to your smartphone and set “Fort McCoy” or another installation as your preferred base.
Date Taken: | 09.15.2023 |
Date Posted: | 09.15.2023 14:41 |
Story ID: | 453554 |
Location: | FORT MCCOY, WISCONSIN, US |
Web Views: | 579 |
Downloads: | 0 |
This work, Army Corps of Engineer-led project at Sparta-Fort McCoy Airport, cantonment area underway for new roofing at Fort McCoy, by Scott Sturkol, identified by DVIDS, must comply with the restrictions shown on https://www.dvidshub.net/about/copyright.