The fiscal year 2023 Transient Training Troops Barracks Project, also called the Fort McCoy East Barracks Project, is now 14 percent complete, said Nathan Butts with the Resident Office of the Army Corps of Engineers at Fort McCoy.
As of Nov. 12, workers with contractor L.S. Black Constructors were putting in more steel framing and building the skeleton of the new barracks. At the beginning of October, the barracks was 10 percent complete.
In a Nov. 8 update, Butts wrote about the ongoing work to the eventual 60,000-plus-square-foot building.
“Structural steel deliveries are ongoing,” Butts wrote. “Decking and rebar placement continues on the south wing of the building. Stairs have been installed on the south side.
“Steel erection continues in the center section of the building. Mechanical, electrical, and plumbing rough-in at the center section of the building is close to complete. And rebar installation to start in the center section,” Butts wrote.
Since May 13, construction of this fourth, $27.3 million barracks project have been in high gear by the contractor who was awarded the project in February. The exact contract amount for the project when it was awarded was $27,287,735.
L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post. They also recently built the new brigade headquarters building located in the same block as the barracks buildings.
Throughout May and well into June a lot of work went into preparing the site for construction. Then going into July actual construction started. During August, footings and foundation walls were built. And by mid-September, they were ready to move upward in building construction, which again began Sept. 18 and continues now.
The contract duration is scheduled for completion in 780 calendar days, Army Corps of Engineer contract documents show.
“Current contract completion date is April 24, 2026,” Butts also wrote.
When complete, the building will be able to house up to 400 people. According to the scope of work, it’s going to be made of permanent construction with reinforced concrete foundations; concrete floor slabs; structural steel frames; steel stud infill; masonry veneer walls; prefinished standing seam metal roofing; heating, ventilation, and air conditioning capabilities; plumbing; mechanical systems; and electrical systems. Supporting facilities include land clearing, concrete sidewalk paving, general site improvements, and utility connections.
The building also is being built with the latest in construction materials and include state-of-the-art physical security and energy-saving measures, the statement of work shows.
In the backdrop of this project is the ongoing third barracks project — a $28 million project that was awarded in June 2023 to BlindermanPower (Construction). That project is currently at 52 percent complete and continuing to be completed swiftly as well, Army Corps of Engineers officials said in early November.
All of this work continues with the master plan for the 1600 block that will include not only the four barracks but also three 20,000-square-foot brigade headquarters buildings — one of which is done — and two 160-room officer quarters, said Master Planner Brian Harrie with the Fort McCoy Directorate of Public Works.
Projects like this also play a part in supporting the economic impact to local economies around Fort McCoy. When looking back the last five years, Fort McCoy’s economic impact has continuously been $1 billion or higher every year to local economies. In FY 2019 it was $1.18 billion, all the way to FY 2023’s $1.38 billion.
See more news about the U.S. Army Corps of Engineers by visiting https://www.usace.army.mil/Media/News.
Fort McCoy’s motto is to be the “Total Force Training Center.”
Located in the heart of the upper Midwest, Fort McCoy is the only U.S. Army installation in Wisconsin.
The installation has provided support and facilities for the field and classroom training of more than 100,000 military personnel from all services nearly every year since 1984.
Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” on Flickr at https://www.flickr.com/photos/fortmccoywi, and on X (formerly Twitter) by searching “usagmccoy.”
Also try downloading the My Army Post app to your smartphone and set “Fort McCoy” or another installation as your preferred base. Fort McCoy is also part of Army’s Installation Management Command where “We Are The Army’s Home.”
Date Taken: | 11.12.2024 |
Date Posted: | 11.12.2024 17:55 |
Story ID: | 485119 |
Location: | FORT MCCOY, WISCONSIN, US |
Web Views: | 59 |
Downloads: | 0 |
This work, Fiscal year ’23-funded East Barracks Project at Fort McCoy rises to 14 percent complete, by Scott Sturkol, identified by DVIDS, must comply with the restrictions shown on https://www.dvidshub.net/about/copyright.