    U.S. Army Corps of Engineers issues permit for rebuild of Francis Scott Key Bridge

    Key Bridge Unified Command leadership briefs U.S. Senate Committee on Environment and Public Works Chairman at Francis Scott Key Bridge site

    Photo By Thomas Deaton | The approach from the northern/Dundalk side of the original Key Bridge structure is...... read more read more

    BALTIMORE, MARYLAND, UNITED STATES

    03.06.2025

    Courtesy Story

    U.S. Army Corps of Engineers, Baltimore District   

    The U.S. Army Corps of Engineers (USACE), Baltimore District, on March 5, 2025, issued its Section 10/404/408 permit decision for the rebuild of the Francis Scott Key Bridge, granting Maryland Transportation Authority permission to construct the bridge that will reconnect the I-695 Baltimore Beltway and improve community accessibility lost following the collapse of the original structure that claimed the lives of six Baltimoreans.

    The Baltimore District Regulatory Branch previously issued two permit verifications in 2024 for preliminary construction activities, explosive demolition, and removal of the remaining bridge structures and continues to participate in weekly interagency meetings on the project.

    “Less than one year after the catastrophic collapse of the Francis Scott Key Bridge, Baltimore District is proud to have provided fair and efficient permitting efforts to enable the construction of a new bridge,” said Baltimore District Commander Col. Francis Pera. “To have both removed the bridge wreckage and issued relevant permits for its reconstruction on this timetable is a testament to our dedicated Regulatory Branch and our mission to support an energetic economy across the Mid-Atlantic.”

    Section 10 of the Rivers and Harbors Act of 1899 requires authorization from the Secretary of the Army, acting through USACE, for construction in or over any navigable water of the United States, including dredging or disposal of dredged materials, excavation, or any other modification. This applies to all structures, from the smallest floating dock to the largest commercial undertaking. It also includes elements like dolphins, trestles, jetties, pilings, and aerial or subaqueous power transmission lines.

    While the construction of the proposed bridge and structures will be performed over and adjacent to the Patapsco River’s Fort McHenry Federal Channel, the work is not anticipated to result in an alteration to the dimensions of the 700-foot-wide and 50-foot-deep channel. Since 1917, the Baltimore District has been congressionally authorized to maintain the Baltimore Harbor and Channels federal navigation project, which includes the Fort McHenry channel, and will continue to do so throughout construction.

    Section 404 of the Clean Water Act requires authorization through USACE for the discharge of dredged or fill material into all waters of the United States, including wetlands. Discharges of fill material generally include placement of fill that is necessary for the construction of any structure, or impoundment requiring rock, sand, dirt, or other material for its construction.

    As currently designed, the bridge replacement will incorporate reinforced pier foundations, pier protection islands, and six dolphins, to permanently impact approximately 12.71 acres of the tidal Patapsco River. A temporary trestle for construction access will also be built and involves the installation of approximately 1,200 36-inch steel piles, covering an above water area of approximately 400,000 square feet, and the top of pile will be located approximately 10 feet above the approximate mean high-water line of the Patapsco River.

    In addition, approximately 300 36-inch temporary mooring or template piles will be installed in the Patapsco River. The trestle and template piles will temporarily impact approximately 9.19 acres of the Patapsco River.

    Geotechnical investigations are ongoing, and test pile operations, pier demolition, and trestle construction are expected to begin in summer 2025. In-water construction of the new bridge will begin in early fall 2025. This project also requires similar permit verification from the U.S. Coast Guard.


    Additional Information

    Baltimore District delivers vital engineering solutions in collaboration with its partners to serve and strengthen the Nation, energize the economy, and reduce disaster risks. Headquartered near Baltimore’s Inner Harbor, Baltimore District provides design, engineering, construction, environmental, and real estate expertise to various important projects and customers. This support spans five states, the District of Columbia, overseas, and the Susquehanna, Potomac, and Chesapeake Bay watersheds. These civil and military missions and diverse engineering services support communities and warfighters while addressing the ever-growing list of emerging national security requirements and ultimately protecting the Nation.

    ###

    NEWS INFO

    Date Taken: 03.06.2025
    Date Posted: 03.06.2025 16:30
    Story ID: 492201