Clay delivery is currently underway at WSLP contract 107 in St. John the Baptist Parish. Clearing, grubbing and burning is about 70% complete. Also, the bypass canal is in the process of being excavated. When completed the levee reach will be approximately 1.7 miles long and the elevation 9.6 feet.