NAS Fallon airfield has a monumental day. After some three and a half years of construction to re-build our Bravo taxiway, today marked the official re-opening. The project provided a full depth replacement of the airfield pavement for Taxiway Bravo on NAS Fallon. With the support of NAVFAC Southwest, the project was completed in two phases and provides a more robust taxiway to support the growing NAS Fallon mission. (November 28, 2023)
• Project Cost: $18.6M
• Contract Awarded: 23 Mar 2020
• Construction Began: Jun 2020
• Contractor placed nearly 20,000 Cubic Yards of Concrete
• Replaced failing pavement, thickened shoulders from 6” to 12” of concrete.
Date Taken: | 01.22.2024 |
Date Posted: | 01.23.2024 13:51 |
Photo ID: | 8206350 |
VIRIN: | 240122-N-EH218-1020 |
Resolution: | 5472x3648 |
Size: | 6.02 MB |
Location: | NEVADA, US |
Web Views: | 50 |
Downloads: | 10 |
This work, Photos Included in CNRSW Region in the Spolight for Naval Air Station Fallon [Image 20 of 20], by Gavin Graham, identified by DVIDS, must comply with the restrictions shown on https://www.dvidshub.net/about/copyright.