Maintenance window scheduled to begin at February 14th 2200 est. until 0400 est. February 15th

(e.g. yourname@email.com)

Forgot Password?

    Defense Visual Information Distribution Service Logo

    New Lock at the Soo: Unlocking the Great Lakes

    220915-A-WR196-1001

    Photo By Carrie Fox | New Lock at the Soo Phase 2 progression between April-September 2022 at the Soo Locks...... read more read more

    SAULT STE. MARIE, MICHIGAN, UNITED STATES

    10.20.2022

    Story by Carrie Fox 

    U.S. Army Corps of Engineers, Detroit District

    SAULT STE. MARIE, Mich., – The U.S. Army Corps of Engineers, Detroit District works on unlocking the Great Lakes by providing a much-needed resiliency at the Soo Locks with the construction of the New Lock at the Soo. The New Lock at the Soo will be the same dimensions as the Poe Lock, 1,200 feet long, 110 feet wide and 30 feet deep.

    Often called the “linchpin” of the Great Lakes navigation system, the Soo Locks are located in Sault Ste. Marie, Michigan between the upper Peninsula of Michigan and the Canadian province of Ontario. The Soo Locks enable bulk carrier vessels to safely bypass the swift-moving St. Marys River rapids where the water drops 21 feet over bedrock in a three-quarter mile stretch. The St. Marys River is the only connecting waterway between Lakes Superior and the lower Great Lakes.

    Before the first lock was constructed in 1798, trade canoes had to be unloaded and portaged around the rapids, taking roughly six weeks to complete. Today, the locks operate 24 hours a day, seven days a week, 42 weeks of the year allowing government, commercial and private vessels to transit safely and more efficiently.

    “Nearly all domestically produced high strength steel, 95%, used to manufacture products like automobiles and appliances is made with iron ore that transits the Soo Locks,” Mollie Mahoney, New Lock at the Soo Senior Project Manager said. “Of the iron ore that transits the Soo Locks, 88% of it is restricted to the Poe lock due to vessel size.”

    The Poe Lock opened in 1968 and will be 62 years old when the New Lock at the Soo is scheduled to be complete in 2030.

    “The reason the Soo Locks have been so reliable over the years is due to the recurring construction of new locks every two or three decades,” LeighAnn Ryckeghem, Soo Locks Operations Manager said. “Up until now the biggest gap was 24 years from opening of the Sabin Lock to the MacArthur Lock.”

    Currently, all major maintenance on the Soo Locks is completed during the federally regulated annual closure period from Jan 15 to March 25. The closure period is driven in part by Great Lakes ice conditions, which typically restricts vessel traffic during this period. “The Detroit District team works long hours in extreme cold and snowy conditions to complete a significant amount of maintenance during this time. The work they perform is unique, especially given the harsh northern Michigan conditions they work in,” Ryckeghem said.

    According to a 2015 Department of Homeland Security Study, “an unanticipated closure of the Poe Lock, the only lock large enough at the Soo Locks to allow passage of the Lakers carrying iron ore, would be catastrophic for the Nation. A six-month Poe Lock closure would temporarily reduce the U.S. gross domestic product (GDP) by $1.1 trillion, resulting in the loss of 11 million jobs: approximately 75% of the U.S. integrated steel production would cease within two to six weeks after a closure of the Poe Lock; approximately 80% of iron ore mining operations would shut down; and nearly 100% of North American appliances, automobile, construction equipment, and farm equipment, mining equipment and railcar production would shut down.”

    Upon completion of the New Lock at the Soo, the facility will have two 1,200-foot lock chambers and one 800-foot lock chamber. After commissioning of the New Lock at the Soo, the Poe Lock will be out of service for several years for major rehabilitation. Once all three locks are operational, one lock will be able to be taken out of service during more favorable periods of weather without affecting navigation.

    The New Lock at the Soo is being built in the footprint of the existing Sabin Lock, the northern most lock on the Soo Locks facility, opened in 1919. The construction program, which includes improvements to the northern approach channel, is occurring in three phases of work. Phase 1 work includes deepening the upstream approach to the northern channel from 24 feet to 30 feet deep so modern vessels can approach the New Lock at the Soo. Phase 2 work includes rehabilitating the upstream approach walls to guide vessels into the New Lock and will allow the vessels to moor on the wall. The existing approach walls in the northern channel are the same age as the existing Sabin and Davis Locks, over 100 years old. Phase 3 work includes demolishing the existing Sabin Lock, infilling the Davis Lock, constructing a new pump well and constructing the New Lock chamber.

    "The Corps of Engineers continues to work hard to maintain the pace and continue to make progress toward New Lock at the Soo total project completion in 2030,” said Mahoney.

    All major phases of the New Lock at the Soo have been awarded. Phase 1 is substantially complete as of August 1, 2022. The $52 million contract was performed by Trade West Construction Co., they removed about 300,000 cubic yards of bedrock and overburden from the north channel. Trade West used mechanical means to remove the material by using rippers and excavators placed on barges to break up and remove the material. The removed material was placed on the Northwest Pier of the Soo Locks facility and will act as a wind break for transiting vessels.

    Phase 2 is currently in the second year of construction and is estimated to be compete in summer 2024. The contractor, Kokosing-Alberici, is placing a series of coffer cells filled with stone aggregate and concrete, in front of the over 100-year-old Sabin Lock walls. The contract is valued at $117 million and includes a total of 52 coffer cells along with several transition walls constructed with steel sheet piles. All the coffer cells and transition walls will be capped with concrete, which will serve as the walking surface of the new walls along the upstream approach channel.

    The base contract for Phase 3 was awarded to Kokosing, Alberici, Traylor, LLC on July 1, 2022. With timely award of all nine contact options, this phase of work is expected to be complete in 2030. The New Lock chamber will be the same size as the Poe Lock to provide resiliency in the operations and maintenance between the New Lock at the Soo and the Poe Lock. There will be some new features on the New Lock at the Soo, such as hands free mooring units.

    “Hands free mooring units act like suction cups that hold the ship in place moving up as the chamber fills or down as it empties,” Rachel Miller, New Lock Supervisory Civil Engineer said. “These units will be a safety upgrade to using line handlers, the current method of mooring ships in the lock chamber.”

    The award of the Phase 3 base contract is a major milestone for the project. Awarding the base allows the contractor to begin a substantial portion of the required work. To date the base contract and one of the nine options have been awarded with a total value of $1.071 billion. With continued funding, the remaining work, valued at $802 million is ready to be awarded over the next three years.

    A major cost increase led to a five-month contract award delay while the Corps of Engineers developed necessary reports to deliver a new cost estimate for reauthorization to Congress. The cost increase root causes include changing market conditions, inflation, a nationwide labor shortage, design modifications and early estimate assumptions. Since the project’s last authorization in 2018 the project’s cost increased from $1 billion to $3 billion.

    “We recognize funding a larger amount for the New Lock at the Soo is a challenge that could potentially result in schedule impacts,” said Deputy District Engineer Kevin McDaniels. “The Corps of Engineers is partnering with industry and federal agencies to find collaborative solutions aimed at addressing the cost impacts to Corps of Engineers programs and projects nationwide.”

    In 2022, the New Lock at the Soo received $478.9 million in the Bipartisan Infrastructure Law (BIL) and $214.2 million in the 2022 BIL addendum (contingent upon the project’s reauthorization at a higher cost in the 2022 Water Resources Development Act). The 2022 BIL addendum funds allow the Corps of Engineers to award some of the remaining $802 million work required to make the New Lock at the Soo fully functional.

    The Soo Locks, recognized as nationally critical infrastructure, continue to receive bipartisan support in Congress for funding the New Lock at the Soo project.

    The Soo Locks complete more than 7,000 vessel passages a year, moving up to 75 million tons of cargos. Moving bulk cargos though the Soo Locks and across the Great Lakes saves more than $3.9 billion per year in freight costs compared to moving the same tonnage by rail or truck. One 1,000-foot vessel can carry the equivalent of seven 100 car trains with a 10,000-ton capacity or 3,000 large trucks with a 25-ton capacity each.

    The New Lock at the Soo will be named by Congress, most likely after it is completed.

    For more information about the New Lock at the Soo project, visit our website: https://www.lre.usace.army.mil/About/Highlighted-Projects/New_Soo_Lock/

    -30-

    NEWS INFO

    Date Taken: 10.20.2022
    Date Posted: 10.20.2022 15:18
    Story ID: 431739
    Location: SAULT STE. MARIE, MICHIGAN, US
    Hometown: DETROIT, MICHIGAN, US

    Web Views: 809
    Downloads: 0

    PUBLIC DOMAIN